1. House and Lot

Think of all the tasks that you perform when you purchase a house and lot. Include any research, decisions considerations, or financial issues that relate to to the purchase. Draw a Gantt and PERT chart chart that shows all the tasks and the estimated duration of each. (Note: You should come up with a task listing as well as it's dependencies)

2. DOSCST - ICSD

At the ICSD Software Development Services you work as a Software Project Manager. You have been asked to conduct user training sessions during the implementation phase for an "SMS Based Student Information Inquiry of DOSCST System". You must develop a specific schedule for the tasks outlined below:
  1. You need to send communication to all College Department's Chair announcing the training session where participations of their students are enjoined (1 day).
  2. After the communication letters sent, two tasks can be begin at the same time
    • you can develop the training material ( 7 days)
    • confirm arrangements for the training facilities (ex. AVR) ( 3 days).
  3. As soon as the training material is complete, you can work on two tasks at once:
    • Arrange to have copies of handout material printed (3 days) and,
    • develop a set of electronic presentation (5 days)
  4. When the electronic presentation is ready, you conduct a practice training session with the faculty that will assist you (2 days).
  5. Finally, when the practice session is over, the handout material is ready and the training facility is confirmed by the DAS, you conduct a training sessions (2 days).
Using PERT technique, develop a chart that shows ES, EF, LS, and LF for the project.

----------------------------happy diagramming -------------------